City of Middletown
Project Type

House Bill Energy Project

Impact

Maintenance and Operational savings totaling over $5.6 million dollars over twenty years.

Background

The City of Middletown was experiencing high operation and maintenance costs throughout the city due to aging equipment and infrastructure and system failures.

Challenges

The biggest challenge experienced was the lack of available funds Middletown had which required the city to use a paid-from-savings program to allow for upgrades to the infrastructure.

Solution

Perfection designed a House Bill Energy Project with a project investment of $4.365 million to replace high voltage switchgear and motor control center equipment alleviating safety and operational concerns at both the Water Treatment and Waste Water Treatment plants. Additionally at the Water Treatment Plant, the plant-wide dehumidification systems were replaced not only to reducing operating costs and eliminate ongoing repair costs but to eliminate other safety concerns due to the failures of the existing systems. A new city distribution pump was implemented to supply fresh water to the city. The pump is operated on a variable speed drive which saves the city significant energy dollars while allowing for future system expansions.

  • Replaced high voltage switchgear and motor control center equipment
  • Replaced plant-wide dehumidification system
  • Installed new city distribution pump
New city distribution pump at water treatment plant
New city distribution pump at water treatment plant
New city distribution pump at water treatment plant

The Perfection crew have done a wonderful job. They work well with our staff and represent your company very well!

Title

Location

Business Type